Weekly Roadwork Report – April 2 – April 8, 2023

 

Bowie County  

  • I-30 – From FM 989 to AR State Line, reconstructing and widening highway, concrete paving in median
  • I-30 – From FM 989 to FM 3419, extension of frontage roads. FM 2148 closed under I-30 bridge
  • I-30 – Eastbound from FM 990, drainage upgrades. Traffic limited to one lane in some areas
  • SH 8 – At Sulphur River, replacing bridges
  • SH 98 – At Anderson Creek, bridge replacement. Traffic restricted to one lane with signal lights controlling traffic through work zone

 

Camp County

  • SL 255 – From FM 1520 to US 271, constructing highway, County Road 2120 detoured

 

Cass County

  • SH 8 – At Sulphur River, replacing bridges
  • US 67 – Widening bridge at Jennings Slough, lanes open to traffic, seal coat scheduled
  • US 59 – From 1.2 miles south of FM 2328N to 1.9 miles south of FM 2328S, resurfacing road, bridge rail improvements. Northbound lane closure

 

Harrison County

  • US 59 – At I-20, replacing bridge. US 59 traffic shifted to southbound lanes
  • I-20 – Concrete pavement repairs. Daytime lane closures
  • I-20 – Bridge maintenance. Lane closures on north frontage road at Mason Creek
  • SH 43 – At Kansas City Southern Railroad in Karnack, widening bridge over railroad. Roadway open
  • FM 3001 – At Little Cypress Bayou Relief. Replacing bridge. Temporary traffic signals in place, lane closure with two-way traffic
  • US 80 – From SL 281 to Tom Brown Parkway, installing safety barrier cable, daytime lane closures

Morris County

  • I-30 – Eastbound at Exit 178, US 259, ramp rehabilitation. Eastbound lane closure

Panola County

  • US 59 (Loop) – From Business 59 north of Carthage to US 79 east, rehabilitating highway. Roadways open, seal coat scheduled
  • SH 149 – 0.8 miles south of SH 315 to US 59. Widening road

 

Titus County

  • US 271 – At Dickson Creek, Big Slough Creek, White Oak Creek & White Oak Creek Relief, replacing bridges

 

Upshur County

  • US 271 – From 5.9 miles north of SH 155 to 1.5 miles north of SH 155, resurfacing road. Lane, shoulder closures
  • US 80 – From Wood County line to 0.3 miles east of SH 155N, resurfacing road